Scope of action | Data backup and documentation Introduction to the Festo Automation Suite software Configuration and parameterisation Remote support during commissioning of 3-axis systems with a safety module System test Checking the electrical connections and the travel path | ||
Customer requirements | Qualified personnel responsible for the machine must be present on the agreed date YJKP kit must be assembled mechanically 24 V logic and 230/400 V load voltage must be made provided Switch and Ethernet cable must be available Local installation of FFT software (see Support Portal) Local administrator rights Local installation of TeamViewer or Bomgar communication software Stable Internet connection |
Work involved on site | 7 working hours | ||
Provision of services | 8-10 days subject to agreement |